Africa (SADC) +27 (0)11 608 3345 | West Africa +233 053 609 4572 | MENA +971 2 447 8319

Case Study – Reverse Osmosis Package Plants – Refurbish and Commission

Construction Industry Reverse Osmosis Package Plants – Refurbish and Commission Problem Statement Our client requested Watericon’s assistance with the scoping and refurbishment of 2 x water treatment containers that have been poorly maintained and possibly non-operational in the last 6-12 months. The project was based in the Limpopo region. Solution Watericon, together with the client’s […]

Case Study – Primary Brine Purification Project – Process Plant – 4.2MLD

Chlor-Alkali Industry Primary Brine Purification Project – Process Plant – 4.2MLD Problem Statement A leading Manufacturer of Chlor –Alkali derivatives in South Africa pursued new technology to reduce the amount of suspended solids in their primary brine purification system. The objective of the technology would eliminate the use of Barium in its current manufacturing process, […]

Case Study – Resin Clean and Recovery – Ion Exchange Plant

Chlor-Alkali Industry Resin Clean and Recovery – Ion Exchange Plant Problem Statement An unpredicted event left the client with Ion Exchange Towers filled with fouled and unusable resin. The client’s only option was sourcing emergency supplies of the specialized resin in record time as to reduce the downtime caused by the substance which caked the […]

Case Study – Primary Brine Purification Process Plant – 4.2MLD

Chemical Industry Primary Brine Purification Process Plant – 4.2MLD Problem Statement Our client’s agricultural division had been having a problem with the quality of the water produced by its processes. The water quality was not meeting the municipal discharge specifications, therefore they contacted Watericon to seek a solution. When the water was tested it was […]

Case Study – Condenser Cleaning – Waste to Energy System – Descaling

Cement Industry Condenser Cleaning – Waste to Energy System – Descaling Problem Statement A leading Cement manufacturer is making use of 2 water sources in their processes, Borehole and River. The challenge is high Hardness which causes scaling in heat exchange units such as condensers, coolers, cooling towers and boilers. Scaling reduces the work rate […]

Case Study – Pilot to Process Water Treatment Plant

Cement Industry Pilot to Process Water Treatment Plant Problem Statement This leading cement manufacturer in South Africa is making use of 2 water sources in its processes, Borehole and River. The challenge faced is high hardness levels in the source waters which causes scaling in heat exchange units such as condensers, coolers, cooling towers and […]

Case Study – Process Water Treatment Plant – 2.6MLD

Cement Industry Process Water Treatment Plant – 2.6MLD Problem Statement This leading cement manufacturer in South Africa is making use of 2 water sources in its processes, Borehole and River. The challenge faced is high hardness levels in the source waters which causes scaling in heat exchange units such as condensers, coolers, cooling towers and […]